Nine cases from concept development, brownfield optimisation and project decision support. Each one: the context, my role, what was hard, what I did and what changed.
Portfolio Integration – 6 Fields
Restructured development across six mature assets and identified shared infrastructure that changed the portfolio investment case.
≈ $48M
Water Injection Re-engineering
Merged a development scope and an asset-integrity programme into one study and replaced a disproportionate redevelopment concept: VRR from 70% to 95% at 80% lower CAPEX.
$3.6M saved
APG Utilisation Pre-FEED
Owner-side Pre-FEED on associated gas: found the facility was gas-limited, selected a right-sized debottlenecking fix and screened about 19 gas-use routes with my own scoring method.
Pre-FEED
EPC Bid Analysis & Contract Strategy
Decomposed bid escalation drivers across a major upstream portfolio and structured scenarios around schedule, FEED maturity, scope and risk allocation.
independent advisory input
Yaro-Yakhinskoye Field Development
Led Pre-FEED and FEED, then supported detailed engineering and execution readiness for facilities tied into live production.
within schedule
South Hub – Brownfield Expansion
Synchronised subsurface and surface decisions so that new facilities could be brought online and integrated into a live producing asset.
signed off the concept
Minor CAPEX Portfolio – Debottlenecking & Integrity
Led FEL for minor CAPEX projects that kept a mature asset running: debottlenecking, integrity and reliability of the gathering system and field facilities.
FEL1–FEL2
Bazhenov Shale Appraisal – Early Production Facility
Coordinated international technical contractors to deliver the early production facility design for an HPHT shale appraisal project on schedule.
EPF design on schedule
Well-Pad & Corridor Siting Method
Built an integrated method for choosing well-pad locations and infrastructure corridors that cut lifecycle cost by 10–50%.
reduction